casebg

30TPH Rock Gold Processing Plant In Australia

30TPH Rock Gold Processing Plant In Australia

Published Date:31 Januari 2026

JXSC has designed & provided a complete set of processing plant machines &all spare parts for Australia customer 30TPH Rock Gold Processing Plant.

This client has their own engineering team to set up this plant, so there is no requirement for our engineer’s site service. While we offer the detailed layout design with base construction drawings accordingly.

Sharer: Hedy

Proyek: 30TPH Rock Gold Processing Plant

Lokasi Proyek: Australia

What Does Hedy Say?

In 2025, we delivered a turnkey 30TPH rock gold processing plant to Australia, featuring a comprehensive five-stage system optimized for fine gold recovery. The solution addressed the client’s specific requirements with pre-fabricated steel structures to reduce Australia’s high labor costs, high-pressure hydraulic roller crushers instead of ball mills for precise particle sizing, and advanced PLC-controlled centrifugal concentration, achieving over 90% recovery of fine gold particles. The plant’s innovative fine sand recovery system achieved 90-95% water recycling while capturing previously lost gold particles, demonstrating our four decades of expertise in creating customized mining solutions that optimize recovery rates while minimizing operational costs and environmental impact.

    Pertanyaan Sekarang

    30TPH Rock Gold Processing Plant In Australia

    1. Customer’s Gold Project Information

    Lokasi: Australia

    Raw ore condition: Rock Gold; Feeding size is -80mm (The large rocks in the front, 400mm, have been crushed to 80mm using a mobile crushing plant ); Gold dissociation size is 0-2mm.

    Persyaratan utama pelanggan: Requested Input capacity is 30TPH; Need gold ore processing plant equipment suitable for very fine gold particles; Need tailings water recycling system; Both the motor-operated and spring-loaded parts require protective covers; Don’t like use ball mill.

    2. Our Process Design & Solution

    Process Flowchart

    30TPH Rock Gold Processing Plant In Australia Flowchart
    30TPH Rock Gold Processing Plant In Australia Flowchart

    Process Description

    This flow sheet includes five parts: feeding, crushing, screening, beneficiation, and tailings dewatering.

    Memberi makan
    1. The raw materials -80mm feed into a hopper by wheel front loader or small dump truck, and there is a pengumpan getaran
    under the hopper to feed the raw stone into the fine jaw crusher evenly.

    Penyaringan
    2. Layar bergetar with 2 layers (25mm & 5mm)
    3. Linear vibrating screen with one layer 2mm

    Menghancurkan
    4. The +25 mm material will be returned to the fine jaw crusher for further crushing.
    5. The 5–25 mm material discharged from the first double roller crusher will be further crushed to below 5 mm.
    6. The 0–5 mm material will then be conveyed to the second double roller crusher for further size reduction to below 2 mm.

    Gravity Beneficiation
    7. The slurry 0-2mm material after the tangki pencampuran will go to the gold centrifugal concentrator for the first gold separation via the slurry pump.
    8. The concentrate from the gold centrifugal concentrator will go to the shaking table for fine gold separation and upgrade the recovery rate.
    9. The tailings will go to the sluice box for catching gold in case some gold flows away.

    Tailings Dewatering
    10. After tailings treatment, the slurry from the sluice box is processed by a fine sand recovery system for filtration and dewatering. The hydrocyclone overflow flows into the clarification pond for water recycling, while the underflow is transported to the ore stockpile via a mobile belt conveyor.

    Main Equipment List

    Tidak. Machinery List Nomor Model Quantity (Set)
    1  Pengumpan Getaran DN380*96 1
    2 #1 Belt conveyor 800*15m 1
    3 Fine Jaw Crusher PEX250*1200 1
    4  #2 Belt conveyor 800*18m 1
    5 Layar Getaran 2YK-1548 1
    6 #3 Return back Belt conveyor 650*13m 1
    7 #4 Belt conveyor 650*15m 1
    8 Pengumpan Getaran Elektromagnetik GZ4 2
    9 Penghancur Rol Tekanan Tinggi 2PGY-800*600 1
    10  #5 Flat belt conveyor under high pressure roller crusher 800*12m 1
    11 Penghancur Rol Tekanan Tinggi 2PGY-800*600 1
    12  #6 Belt conveyor 650*15m 1
    13 Linear Vibrating Screen 1500*4500 1
    14 #7 Belt conveyor 650*15m 1
    15 Tangki Pencampuran XB2000 1
    16 Pompa lumpur 4/3 inch 1
    17 Pompa Air Cuci Belakang IS100 1
    18 Meja Goyang 4500*1850mm 1
    19 Kotak pintu air 6m * 1m * 0,3m 1
    20 Fine Sand Recovery Machine 1536 1
    21 #8 Mobile Belt Conveyor with Motorised Wheels 800*15m 1
    22 Dandong Centrifugal Separator GTD50 1
    23 Tungku Emas 35A 1
    24 Electrical control cabinet Full Set 1

    3. This Processing Plant Application

    • Ideal Applications

       

      • Without a concrete foundation, a steel structure is needed to compensate for the elevation difference in the mining area.
      • The gold particles are mostly very fine-grained.
      • Raw ore: Gold oxide
    • Not Recommended For

       

      • Ultra-hard ore that lacks pre-treatment processes
      • Raw ore is rock gold sulfide, and with various other precious metals.

    4. Questions & Answers

    Q1: Why does this customer want the factory to fabricate the steel structure completely before shipment? Because usually, customers weld it themselves on-site, with the factory only supplying the steel materials.

    A: Because labor costs in Australia are very high; for example, a skilled welder earns approximately 700-1000 Australian dollars per day.

     

    Q2: What kinds of feeding method for this 30TPH Rock gold processing plant? Trucks, excavators?

    A: Manual truck feeding raw material.

     

    Q3: With truck feeding, what size should the raw material silo be designed for a capacity of 30 TPH?

    A: Working 10 hours per day, need 25m3 raw hopper.

     

    Q4: How will the 25m3 large storage bins be shipped after welding?

    A: The factory welds and assembles a complete hopper, then cuts it in half and ships it in 40FR containers.

     

    Q5: When ordering a customized pabrik pengolahan bijih emas, what supporting services will the manufacturer provide? Is technical support available afterwards?

    A: Pre-sales: We have a dedicated laboratory where customers can send ore samples.
    Our factory will conduct mineralogical analysis and small-scale tests, design a customized beneficiation process and equipment configuration plan, and provide detailed process flow diagrams and investment budgets.
    After placing an order, we arrange equipment production, transportation, and send 1-2 engineers for on-site installation and commissioning. A professional technical team provides comprehensive guidance to ensure the equipment is put into normal operation. We also train mine operators to master equipment operation and daily maintenance skills.
    After-sales: To ensure long-term stable production at the mine.
    We provide 24-hour online technical support to address technical problems during production. A professional technical team provides comprehensive guidance to ensure the equipment is put into normal operation.

     

    Q6: What specific role does the fine sand recovery integrated machine play in the tailings dewatering process of a hard rock gold processing plant?

    A: The fine sand recovery integrated machine is the core equipment for dewatering and dry discharge of hard rock gold tailings. It is designed to address the problem of high proportions of fine sand (0.074~0.5mm) and associated fine gold particles in hard rock gold tailings, where fine sand is easily lost with the tailings water. In the tailings dewatering process, it performs three core functions: dewatering, fine sand recovery, and water recycling.

    Q7: What is the water recovery rate of rock gold tailings after treatment with the integrated fine sand recovery machine? Can the recovered water meet the production needs of the rock gold processing line?

    A: The water recycling rate of rock gold tailings treated by the integrated fine sand recovery machine can be stably maintained at 90% to 95%; if a tailings thickener is used for pre-treatment to concentrate the tailings slurry to a concentration of over 40% before entering the integrated machine, the water recycling rate can be increased to over 95%.

     

    Q8: In the fine crushing stage of gold ore before gravity separation, what makes high-pressure hydraulic roller crushers superior to ordinary fine crushing equipment? Why are they suitable for the fine crushing needs of gold ore?

    A: Precise and uniform discharge particle size, suitable for gravity separation and liberation: Relying on the high-pressure hydraulic system to precisely control the gap between the rollers, the discharge particle size can be steplessly adjusted within 0-20mm, and the finished product particle size is uniform without over-crushing.
    Anti-clogging and overload protection, suitable for the characteristics of gold ore.
    Wear-resistant roller surface, long service life, reducing the frequency of roller surface replacement, and significantly reducing the cost of wear parts and downtime for maintenance.
    Low energy consumption + low dust, and the equipment comes with a sealed dust cover, so there is no dust overflow during the fine crushing process.

    30TPH Rock Gold Processing Plant In Australia

    Q9: Compared to traditional manual or semi-automatic discharge mining centrifuges, what are the core advantages of using fully automatic PLC-controlled centrifuges for alluvial gold recovery? What benefits can they bring to actual mining operations?

    A: PLC fully automatic ore discharge eliminates the need for manual supervision, saving labor costs. The PLC system automatically controls the entire process of ore feeding, sorting, and discharge.
    Precise ore discharge significantly improves gold recovery rate: The recovery rate of fine gold particles (0.01-0.5mm) can reach over 90%.
    Compatible with production line integration, achieving automation of the gravity separation line: The PLC control system can automatically adjust the processing capacity of the centrifuge according to the upstream ore feed volume.
    Easy maintenance + low energy consumption, reducing operating costs: Core components such as the drum are made of wear-resistant stainless steel, ensuring a long service life. The equipment uses variable frequency speed control, and daily maintenance only requires periodic replacement of seals and lubricating oil. There are no complex or easily damaged parts, resulting in low long-term operating costs.

    5. Production, Shipping & On-site

    30TPH Rock Gold Processing Plant In Australia - Manufacture

    Manufacturing Photos

    30TPH Rock Gold Processing Plant In Australia -Delivery

    Delivery Photos

    Why The Client Chose JXSC?

    • +40 years of manufacturer history of all kinds of mining machinery(including crushing plant &mineral processing plant).
    • Customize Customer’s Minerals Processing Plant Solution & Provide a complete set of crushing & processing plant machines (from A to Z). Especially has long years of professional experience in rock gold processing plant design.
    • Provide Professional Engineer After Sales Installation and commissioning Service & 24H/7DAY online service.
    • Have a professional laboratory for all kinds of ore sample testing.
    • Has a sub-company & warehouse in Nigeria, Indonesia, and Zimbabwe.
    • 15 years of Professional Export Experience to Worldwide more than 100 countries.
    • The company is ISO certificate approved, Products has CE approval.
    30TPH Rock Gold Processing Plant In Australia
    30TPH Rock Gold Processing Plant In Australia
    30TPH Rock Gold Processing Plant In Australia

    JXSC adalah produsen peralatan pertambangan profesional & ahli solusi bijih pertambangan. Ini memiliki banyak kasus yang berhasil seperti pabrik emas, solusi berlian, dll., Jika Anda membutuhkan layanan seperti itu, silakan hubungi kami.

    Hubungi Kami Sekarang

    Jika Anda memiliki pertanyaan tentang produk kami, silakan isi formulir di bawah ini, dan kami akan menghubungi Anda dalam waktu 24 jam. Yakinlah bahwa kami tidak akan mengungkapkan informasi Anda kepada siapa pun.

      Konsultasi Gratis Dengan Tim Penjualan dan Teknik Kami





      • Informasi Anda aman. Periksa pemberitahuan privasi untuk detail lebih lanjut.

      • Kami tidak menawarkan pekerjaan dan membeli atau menjual mineral. Kami HANYA menjual peralatan pertambangan!

      • Kami tidak tertarik dengan kerja sama dan investasi!

      </div
      Ikhtisar Privasi
      logo

      Situs web ini menggunakan cookie agar kami dapat memberikan Anda pengalaman pengguna terbaik. Informasi cookie disimpan di browser Anda dan menjalankan fungsi seperti mengenali Anda saat Anda kembali ke situs web kami dan membantu tim kami untuk memahami bagian situs web mana yang menurut Anda paling menarik dan berguna.

      Cookie yang Sangat Diperlukan

      Strictly Necessary Cookie harus diaktifkan setiap saat agar kami dapat menyimpan preferensi Anda untuk pengaturan cookie.

      Analytics

      Situs web ini menggunakan Google Analytics untuk mengumpulkan informasi anonim seperti jumlah pengunjung ke situs, dan halaman yang paling populer.

      Mengaktifkan cookie ini akan membantu kami meningkatkan situs web kami.