Compact & Scalable Lithium Plant for Small Miners

Published time:19 Mei 2026

Introduction: Democratizing Lithium Mining for Small Operators

As global lithium demand surges, JXSC has engineered a breakthrough solution bringing industrial-grade processing to small miners. Our commissioned 120TPD lithium processing plant in Nigeria demonstrates how compact, modular systems can deliver 85-90% recovery rates while maintaining scalability to 240TPD.

 

120TPD Lithium Processing Plant Case Study from Nigeria

Nigeria’s mining sector is growing, and small-scale hard rock lithium mining is gaining traction. Recently, JXSC designed and supplied a 120-ton-per-day (TPD) lithium processing plant for a local mining company. This tailored solution processes spodumene ore efficiently, with the flexibility to upgrade to 200TPD or 240TPD in the future.

Let’s break down the project overviewprocessing flowkey equipmentdan customer benefits.

Gambaran Umum Proyek

  • Lokasi: Nigeria
  • Client: Local small-scale lithium mining company
  • Ore TypeSpodumene(2% Li₂O grade, max feed size: 200mm)
  • Kapasitas Pengolahan120TPD(expandable to 200-240TPD)
  • Key RequirementEasy operation, high recovery, cost efficiency

 

120TPD Lithium Processing Plant
120TPD Lithium Processing Plant

 

Processing Flow & Equipment

1. Feeding & Crushing System

Purpose: Reduce large-sized spodumene ore (≤200mm) to ≤20mm for grinding.

Proses: Two-stage crushing (12 hours/day)

Peralatan: Chute Feeder → Penghancur Rahang (Primary) → Fine Jaw Crusher → Vibration Screen (20mm mesh)

  • Pengumpan Saluran→ Continuously regulates ore feed to prevent clogging.
  • Primary Jaw Crusher→ Breaks down ore to 40-100mm (first-stage crushing).
  • Vibration Screen (20mm mesh)→ Screens out ≤20mm material (sent to stockpile).
  • Fine Jaw Crusher→ Further crushes oversize (+20mm) material.

Keluaran: 0-20mm fine ore for grinding

Why only 10 hours of crushing?

  • Efisiensi tinggi– Short crushing time reduces power consumption.
  • Optimized grinding– Finer crushing increases ball mill throughput.

2. Ball Mill Grinding System

Tujuan: Grind 0-20mm spodumene ore to 200mesh slurry (75-80% fineness) for lithium liberation.
Process: 24-hour continuous operation
Peralatan: Electromagnetic Feeder → Ball Mill → Spiral Classifier

  • Pengumpan Elektromagnetik → Automatically controls feed rate (5TPH) for steady grinding
  • Ball Mill → Uses steel balls to pulverize ore into fine powder (200mesh target)
  • Pengklasifikasi Spiral→ Separates qualified slurry from coarse particles
    Overflow (200mesh): Sent to flotation
    Underflow (coarse): Returned to ball mill for re-grinding

Output: Uniform 200mesh slurry (critical for flotation efficiency)

Why a ball mill instead of a hammer crusher?

  • Hammer crushers max out at ~2mm particles (insufficient for lithium flotation)
  • Ball mills achieve 70-80% ≤200mesh fineness for optimal mineral liberation

Why a pengklasifikasi spiral?

  • Ensures only properly ground material (<200mesh)proceeds to flotation.
  • Coarse particles return for re-grinding, creating a closed-loop system.

 

pabrik bola
pabrik bola

 

3. Mud Water Removing System

Tujuan: Eliminate clay/ultrafines that harm flotation performance
Process: 24-hour cyclone separation
Peralatan: Hydrocyclone Array

Hydrocyclone Operation:

  • Overflow (mud water): Discharged to the tailings pond
  • Underflow (cleaned slurry): Pumped to flotation mixing tanks

Criticality:

  • Prevents reagent waste in flotation
  • Raises Li₂O recovery by 8-12%

What if we skip the hidrosiklon

  • Uneven particle size 
  • Increased flotation reagent waste 
  • Lower lithium recovery

4. Flotation System

Tujuan: Separate lithium minerals from gangue via froth flotation
Process: 3-stage selective separation (24h operation)
Peralatan: Mixing Tanks → Flotation Machines (Roughing/Scavenging/Cleaning)

Detailed Sequence:

  • Mixing Tanks (×2): Ore + reagents (pH modifiers/collectors) homogenized for 5-8 minutes
  • Roughing Flotation (4 cells): Recovers 60-70% Li₂O in primary concentrate
  • Scavenging Flotation (8 cells): Recovers residual lithium from tailings (boosts total recovery to 85-90%)
  • Cleaning Flotation (5-8 cells): Upgrades concentrate to 5-6% Li₂O through 2-3 purification cycles

Water Consumption: 300T/day (80% recycled from thickeners)

5. Li₂O Concentrate Dewatering System

Tujuan: Produce dry, shippable lithium concentrate (~8% moisture)
Process: Two-stage water removal
Peralatan: Thickener → Disc Vacuum Filter → Belt Conveyor

  • Thickener: Increases slurry density from 30% → 60% solids via gravity settling
  • Disc Vacuum Filter: Removes 92% water through suction filtration; Achieves final moisture content of 8-12%
  • Belt Conveyor: Transports packaged concentrate to storage (bags/bulk)

Key Advantage

  • Filter water is fully recycled to the processing circuit
  • Compact footprint vs. traditional drying methods 

Tailings Management Options

Standard Solution: Tailing pond sedimentation
Upgradable Option:

  • Plate Filter Press System→ Produces stackable, dry tailings cake
  • Includes:Tailing thickener + Tekan filter + Conveyor

Cost-Benefit

  • Reduces environmental footprint
  • Enables tailings reprocessing (future lithium extraction)

Current Setup

  • 120TPD plant uses a simple pond system
  • Upgrade-ready for future dry stacking needs

Equipment Configuration

Equipment For 120TPD Lithium Plant
NO. Nama Produk Nomor Model Quantity (Set)
1 Pengumpan Saluran 600*500 1
2 Primary Jaw Crusher PE250 * 400 1
3 Konveyor sabuk 650*15m 5
4 Fine Jaw Crusher PEX150*750 1
5 Layar Bergetar 1530 1
6 Konveyor sabuk 650*10m 1
7 Pengumpan Getaran Elektromagnetik GZ1 1
8 Ball Mill MQZ1530 1
9 Electronic weight machine 650 1
10 Pengklasifikasi Spiral FG-10 1
11 Pompa lumpur 3/2 inch 2
12 Tangki Pencampuran 1m*1m 2
13 Mesin flotasi SF-1.2 17
14 Hidrosiklon FX100 1
15 Slurry Pump for hydrocyclone 3/2-AHR 2

 

Technical Support & Maintenance

Engineer Services

  • Fee: $150/day per engineer

Typical Duration

  • Basic commissioning: 15-20 days
  • Full optimization: 1-2 months

Critical Training Topics

  • Ball mill media replenishment schedule
  • Flotation reagent dosing calibration
  • Hydrocyclone pressure adjustments

Who Is This Plant For?

  • Small-medium lithium miners (120-240TPD).
  • Hard rock (spodumene/lepidolite) processing.
  • Not suitable for sand-based lithium or large-scale industrial plants. 

Why Customers Choose JXSC?

  • Customized Solutions→ Tailored for small-medium miners.
  • 40+ Years Experience→ Reliable mineral processing experts.
  • ISO & CE Certified→ High-quality, compliant machinery.
  • After-Sales Support→ Installation guidance & troubleshooting. 

Final Customer Feedback

  • Stable operation
  • Met production targets
  • Satisfied with recovery rates 

Kesimpulan

Ini 120TPD lithium processing plant demonstrates JXSC’s ability to deliver cost-efficient, high-recovery solutions for small-scale miners. By optimizing crushing, grinding, and flotation, we ensure maximized lithium extraction dengan minimal operational hassles.

Interested in a similar solution? Contact us for a customized proposal!

    Hubungi Kami Sekarang

    Ikhtisar Privasi
    logo

    Situs web ini menggunakan cookie agar kami dapat memberikan Anda pengalaman pengguna terbaik. Informasi cookie disimpan di browser Anda dan menjalankan fungsi seperti mengenali Anda saat Anda kembali ke situs web kami dan membantu tim kami untuk memahami bagian situs web mana yang menurut Anda paling menarik dan berguna.

    Cookie yang Sangat Diperlukan

    Strictly Necessary Cookie harus diaktifkan setiap saat agar kami dapat menyimpan preferensi Anda untuk pengaturan cookie.

    Analytics

    Situs web ini menggunakan Google Analytics untuk mengumpulkan informasi anonim seperti jumlah pengunjung ke situs, dan halaman yang paling populer.

    Mengaktifkan cookie ini akan membantu kami meningkatkan situs web kami.