JXSC has supplied a complete set of mineral processing equipment and all necessary accessories for a 200-ton-per-day Rock Gold CIL (Carbon-in-Leach) Processing Plant to our client in Burkina Faso. The client is a well-established local gold mining company with an experienced engineering team; they were able to handle the plant installation independently, eliminating the need for our engineers to provide on-site installation services.
To ensure successful project execution, we provided:
- Detailed Process Flow Design – Optimized for Burkina Faso’s rock gold ore characteristics
- Comprehensive Foundation Construction Drawings – Including equipment layout and structural requirements
- Complete Equipment Supply – All machinery and spare parts for the entire CIL process